The construction on Locust Avenue has been delayed for the last few weeks due to New York State encountering unexpected conflicts with an existing sewer main and Verizon duct bank. They are in the process of resolving those issues and anticipate construction will start up again in August. We thank you for your cooperation and as we receive updates will keep all our Village residents and guests informed.

 